01How much capacity, really

The 2023 master plan expected peak demand of about 50 GW by 2040.[1] The 2026 plan’s business-as-usual case is about 41 GW, and the Centre for Policy Dialogue argues that 2040 demand should be planned at 30 GW or less.[2] With a reserve margin above 60 percent in FY2024-25,[3] the next decade is less about adding megawatts than about replacing expensive ones.

02Solar, with storage

Storage decides how much solar the evening peak can use
Storage decides how much solar the evening peak can usePhoto: Unsplash

Solar is the quickest capacity to build and needs no imported fuel. IEEFA’s roadmap calls for 5,500 MW of renewables and 500 MW of three-hour battery storage by 2030, alongside phasing out 1,000 MW of old gas plants.[4] The World Bank makes the same case for utility-scale and rooftop solar, backed by investment in the grid.[5]

Storage is what turns midday solar into evening power, when demand peaks. Without it, more solar mainly displaces daytime gas.

03Efficient gas, not more oil

Gas will remain the backbone for years, but the fleet can use it better. IEEFA recommends cutting oil-fired generation from about 11 percent of the total to 5 percent, and adding no new fossil capacity.[3] Repowering old gas units to combined cycle gets more electricity from the same fuel.

04Wind

Bangladesh has real wind potential: a 2018 NREL study found more than 30 GW of gross potential. The first large wind farm, 60 MW at Cox’s Bazar, has so far run at a capacity factor of about 17 percent, below the 23 percent expected.[6] Wind needs better resource data and a clear procurement route before it can grow.

05Regional hydro and nuclear

Hydropower from Nepal already reaches Bangladesh through India: 40 MW during the wet season, with a further 20 MW agreed but awaiting approval.[7] Regional trade can add clean power without using land at home, if the transmission and agreements follow.

The first 1,200 MW unit at the Rooppur nuclear plant completed fuel loading in May 2026.[8] Nuclear adds large, steady capacity, but it is expensive and takes many years to plan and build.

06A sensible order

Table 1 · What to build, in what order
PriorityWhatWhy
1Solar with storageNo fuel imports, fastest to build
2Grid and interconnectionLets existing and new plants deliver
3Efficient gas and repoweringMore power from scarce gas
4Wind and regional hydroSpreads supply beyond solar
5Retire oil and old steam unitsRemoves the most expensive units first

“The next plant Bangladesh builds should lower the average cost of a unit, not raise it.”

Abdullah Bin Hossain

For sponsors, that is the test to apply before any feasibility study: will this plant make electricity cheaper, more secure or cleaner than what it replaces?