01The stages

Every developer’s guide, from the IFC’s guide to utility-scale solar onwards, describes the same sequence.[1] In Bangladesh each stage has its own offices and documents.

Table 1 · From idea to commercial operation
StageWhat it producesMain counterparts
Pre-feasibilityScreened sites, a route to market, first numbersGrid company, land offices
Site and landLand control, survey, NOCsLand offices, local administration
FeasibilityThe technical, financial and regulatory caseConsultants, lenders
ApprovalsLicences and clearancesPower Division, BPDB, BERC, DoE, BIDA
ContractsPPA or MPPA, grid agreements, EPC contractBPDB or buyers, PGCB, EPC contractor
FinancingFinancial closeBanks, Bangladesh Bank, BIDA
ConstructionCommissioning and CODEPC contractor, grid company

02The approvals that matter

Generation licence

Under the Bangladesh Energy Regulatory Commission Act 2003, generating electricity for sale needs a licence from BERC.[2]

Environmental clearance

The Environment Conservation Rules 2023 classify projects by risk. Large power plants are in the Red category, which needs a site clearance, an environmental impact assessment and then an Environmental Clearance Certificate from the Department of Environment.[3]

Foreign investment and borrowing

Thermal or solar, every plant needs the same licence, clearance and financing approvals
Thermal or solar, every plant needs the same licence, clearance and financing approvalsPhoto: Unsplash

Foreign investors register with the Bangladesh Investment Development Authority (BIDA). Foreign loans have gone through a BIDA scrutiny committee chaired by the Bangladesh Bank governor.[4] Since September 2026, BIDA-registered companies no longer need a separate Bangladesh Bank approval for medium and long-term foreign borrowing.[5]

Tax incentives

Renewable projects that reach commercial operation between July 2025 and June 2030 can claim a full income tax exemption for ten years, then 50 percent for three years and 25 percent for two, with a no-objection certificate from the Power Division.[6]

03Where the time goes

The official picture and the real one differ. According to a chamber of foreign investors, investors deal with 23 agencies; approvals officially meant to take 76 days often take six to twelve months, and a land title transfer can take 260 days.[7]

Payment is the risk that remains after construction. Dues owed to private power producers passed Tk 27,000 crore in late 2025.[8]

The timelines of recent plants show the pattern. Summit’s 583 MW Meghnaghat II plant signed its PPA in March 2019 and reached commercial operation in April 2024.[9]

04How to shorten the path

  1. Start with the site and the grid. Most delays trace back to land and the connection. Verify both before spending on anything else.
  2. Build one complete file. A feasibility study, land records and grid studies that answer every office’s questions the first time.
  3. Map every approval and its owner. Know which office signs what, in what order, and follow each file until it is signed.
  4. Plan the money early. Local and offshore accounts, foreign loan approvals, tax exemptions and repatriation, set up before they are needed.
  5. Audit before you submit. An independent check of the technical, legal and financial file catches the gaps a reviewer or lender would find.

“A project is built twice: first on paper, then on site. The paper takes longer.”

Abdullah Bin Hossain